DragonFly-2.1.1.500.ged1bfc DragonFly_RELEASE_2_2 created
Matthew Dillon
dillon at apollo.backplane.com
Tue Feb 3 17:18:05 PST 2009
The release schedule is to release approximately two weeks from
today. As Simon says, fixes should continue to be committed to
the master branch. Simon and/or I will merge them into the release
branch and I will do the needed release engineering on the release
branch to adjust the version info, etc.
master is in soft-freeze for the next week and a half. Only commits
that we want to get into release should be made to master. When we
get closer to the actual release near the end of next week the master
branch will be unfrozen.
I will adjust version information in the release branch tomorrow
(Wednesday) so bulk builders can get the builds started and so we can
get the nrelease builds cleaned up and fully operational.
We will need a pkgsrc base to work from. Hasso, what do you suggest?
-Matt
More information about the Users